Roads Projects

The Shire of Morawa provides a comprehensive works schedule to ensure that our Roads are well maintained. From time to time unexpected works can crop up in response to special circumstances.

To assist in keeping you informed of where to expect to see our machinery please see our general Schedule of Planned Works listed below.

Schedule of Planned Works up to the 30th of June 2020 

October 2019 to December 2019

  • Morawa Yalgoo Road
    • Widen and Seal the Road to 7 metres
  • Burma Road
    • Construction of Road and Gravel Sheeting

December 2019 to February 2020

  • Nanekin Road
    • Construction of Road and Seal to 7 metres

February to April 2020

  • Nanekin Road
    • Construction of Road and Seal to 7 metres

April to May 2020

  • Canna North East Road
    • Construction of Road and Gravel Sheet

May to June 2019

  • Canna North East Road
    • Construction of Road and Gravel Sheet

If you experience any issues or concerns with our roads then please pop in to the Shire of Morawa Administration centre and speak to one of our team. Alternatively you may ring us on 9971 1204 or email us on admin@morawa.wa.gov.au